R&M provided construction administration services for this federally-funded project that improved the structural section with a foamed asphalt base and new asphalt surfacing for Runway 16/34, Taxiways A, D and H, Taxilane B and the aprons. Construction began in 2021 and was completed in fall 2022. The components included new runway and taxiway lighting systems, runway markings and navigational aids. The project also included installing an extensive rip rap revetment along the Kuskokwim River off the end of Runway 34.
Services for this Project